Transformer Supply in 2026: A Constraint That’s Reshaping Grid Development

As electricity demand accelerates across the U.S., transformers have emerged as one of the most closely watched constraints in grid development. New analysis suggests the issue may be less about a single equipment shortfall and more about how the power industry plans, procures, and sequences infrastructure.

According to Wood Mackenzie, U.S. power transformer demand has increased more than 100% since 2019, driven by data centers, electrification, renewable integration, and the replacement of aging grid assets. More than half of U.S. distribution transformers are already beyond their expected service life, creating steady replacement pressure on top of new construction.

Transformer Manufacturing Facility

Manufacturers have announced nearly $2 billion in new North American capacity, lead times for large power transformers remain elevated, often exceeding two years. Costs have also risen sharply, with power transformer prices up more than 70% since 2019.

Some market participants argue the shortage narrative may be overstated. They point to alternative sourcing pathways and procurement practices that can reduce timelines if utilities and developers are willing to move earlier and broaden supplier engagement. This tension suggests that transformer availability is not only a manufacturing issue, but a planning and coordination challenge.

What is clear is that transformers are not an isolated bottleneck. Switchgear, breakers, and other transmission and distribution equipment are experiencing similar pressure as multiple sectors compete for the same factory capacity.

Map of the major U.S. electric grid regions, also known as Independent System Operators (ISOs) and Regional Transmission Organizations (RTOs)

As grid expansion, data center development, and electrification continue, access to critical equipment, and the ability to secure it early, is becoming a defining factor in which projects move forward and which remain delayed.